While InQuik is still in development for under-rail use in the USA, our bridges are excellent for constructing over-rail. 

 

The Australian Rail Track Corporation (ARTC), needed to replace a deteriorating timber structure spanning an active railway line, prioritizing durability and construction efficiency.

 

Leveraging the InQuik Bridge System, the team installed a reinforced concrete bridge that was cast-in-place, without the need for track possession or service disruption.

 

The bridge was completed in just two weeks by a 3-man crew, highlighting significant benefits using InQuik’s lightweight, cast-in-place system that not only saves time, but also saves money. Whether it’s a remote location with limited access like this project, or an urban environment, complex projects can be safely and rapidly completed with minimal impact to the community and other infrastructure.

How it Works

Pre- Engineered, Pre-Certified and Pre-Fabricated Bridge Components

Fast installation

Lightweight panels can be placed into position using small cranes or local excavators. Typically takes 3 – 5 days to install the bridge.

Easy Transport

Panels are designed to be efficiently stacked and transported in the form of a shipping container.

Certified & Durable

75+ year design life, with engineering certified by ARUP to the AASHTO LRFD Bridge Design Specifications – 9th Edition.

Low Maintenance

Minimal maintenance with no deck joints, longitudinal joints, tie-downs or bearings.

Safe and fish-friendly

Construction from above, improving safety and reducing environmental impact. No propping, bracing, or any work within the waterway required.